Table 7 Supplemented table of critical success factors

From: Extended risk-analysis model for activities of the project

Risk analysis

Risk management

No.

WBS code/Activity/Problem

Event probability EP

Consequence estimate EC

Incidence estimate EI

Risk level RL3

Measures

Responsibility

Indicator

P – preventive

K - corrective

1.

Activity 1/Problem A

3

2

4

24

   

2.

Activity 2/Problem B

2

4

4

32

P – Prevent. measure 1

Project manager

 

j.

Activity j/Problem N

4

5

5

100

P – Prevent. measure 2

Manager of development

X days delay

P – Correct. measure 1

n

Activity n/Problem x

4

4

3

48

P – Measure 3

Project manager